Appendix G Baseline HVAC System Selection: How Systems 1 to 13 Are Assigned

ASHRAE 90.1 Appendix G baseline HVAC system selection
The baseline system is chosen by a table, not by what the design team drew.

In an ASHRAE 90.1 Appendix G model, the proposed building is modelled as designed. The baseline building is not. Its HVAC system is assigned by a table, and that assignment has more influence on the final savings figure than almost any other baseline decision. A wrong baseline system is also one of the most common reasons a LEED energy model comes back from review.

What decides the baseline system

In recent editions of the standard, four things decide the baseline system: the building type, the number of floors, the conditioned floor area and the climate zone. The proposed design's HVAC system plays no part. A building designed with VRF, chilled beams or ground-source heat pumps still gets the baseline system the table gives it.

The climate zone decides the heating fuel. In warm zones (0 to 3A) the baseline uses electric heating: heat pumps or electric resistance. In the remaining zones (3B, 3C and 4 to 8) the baseline uses fossil fuel heating. Editions before 2016 chose the heating fuel from the proposed design's heating source instead, so check which edition applies before starting.

The selection table in outline

Each row gives a fossil fuel system for the colder zones and an electric system for the warmer ones:

System 11 (single-zone VAV) is reserved for large computer-room loads.

The exceptions that add more systems

Few real buildings fit one row. The standard lists exceptions that assign additional baseline systems to parts of the building:

Each exception needs to be applied on purpose and written down. Reviewers ask for the reasoning.

How many systems, and what plant

The single-zone systems (1 to 4, and 9 to 13) are modelled one per thermal block. The VAV systems (5 to 8) are modelled one per floor. Plant follows fixed rules. For the chilled-water systems, the number and type of chillers depends on the baseline peak cooling load: one screw chiller up to 300 tons, two screw chillers between 300 and 600 tons, and two or more centrifugal chillers at 600 tons and above. Hot-water systems get two equal boilers when the plant serves more than 15,000 ft², otherwise one.

Sizing and the details that follow

Baseline equipment is autosized from the baseline loads and then oversized by 15% for cooling and 25% for heating. Supply airflow is based on a 20°F difference between supply air and room setpoint. Fan power comes from a formula, not from the proposed fans. Economizers are included or excluded by climate zone. None of these values is copied from the proposed design.

The baseline must then pass the same unmet load hours test as the proposed model.

Common mistakes

The takeaway

Baseline system selection is a procedure, and it should be documented as one: building type, floors, area, climate zone, the row chosen, and every exception applied. A model that shows this trail gives the reviewer little to question, and gives the design team a savings number they can rely on.

Need an Appendix G model reviewed or built?

We build and check ASHRAE 90.1 Appendix G baseline and proposed models for LEED and code compliance, with the baseline system selection documented step by step. Let's talk.

Get in touch