An energy model can report low energy use for a bad reason: the HVAC system is simply not keeping the building at setpoint. A system that fails to heat or cool uses less energy than one that does its job. Unmet load hours are the check that catches this, and reviewers look at them before they look at the savings.
What an unmet load hour is
ASHRAE 90.1 defines an unmet load hour as an hour in which one or more zones is outside its thermostat setpoint by more than a small tolerance. If ten zones miss setpoint in the same hour, that is still one unmet hour for the building. Heating and cooling hours are added together.
The 300-hour rule
Appendix G limits unmet load hours to 300 of the 8,760 hours in the year, for the baseline model and for the proposed model separately. Some editions also limit how far the proposed model's unmet hours may exceed the baseline's. LEED and most code compliance reviews apply the same test.
The rule exists for fairness. If the baseline keeps every room comfortable while the proposed lets rooms drift, the "savings" are partly discomfort. Both models have to deliver the same service.
Where to find them
In EnergyPlus and tools built on it, such as OpenStudio and DesignBuilder, the summary reports list the time setpoint was not met during occupied heating and occupied cooling, for the facility and for each zone. The zone table matters most. It shows whether the problem is one difficult room or the whole building.
Check the reporting tolerance too. The EnergyPlus default is tight (0.2°C). Small, harmless control deviations then count as unmet hours. Setting the tolerance in line with the thermostat throttling range is normal practice and should be stated in the report.
The usual causes
- Undersized equipment — sizing design days that are milder than the weather file, or sizing factors left at 1.0.
- Setback recovery — the system starts when occupancy starts, and the first hours of each day miss setpoint. This is the most common cause of heating unmet hours.
- Schedule conflicts — the thermostat asks for comfort at a time when the fan or plant schedule is off.
- Plant limits — chilled or hot water that is too warm or too cool, pumps that are too small, or a two-pipe system in the wrong mode.
- Airflow limits — VAV boxes with a maximum that is too low for the zone peak, or minimum flows and reheat that cannot hold heating setpoint.
- Zoning — one thermostat serving spaces with very different loads, such as a corner room grouped with interior space.
- Heat pump limits — capacity loss, defrost or lockout at low outdoor temperature with no supplemental heat modelled.
How to fix them properly
Start with the zone table and find the worst zones. Then look at when the hours occur: early morning points to recovery, peak afternoons point to capacity, and all-day drift points to controls or plant.
- Add optimum start or begin the HVAC schedule an hour or two before occupancy, as the real building would.
- Confirm that sizing design days match the design conditions for the site and that the weather file is for the same location.
- For the baseline, apply the Appendix G oversizing factors (15% cooling, 25% heating) before anything else.
- Check thermostat, fan and plant schedules against each other.
- Correct zone airflow limits and supply temperatures.
For the proposed model, be careful. It should represent the design. If the design capacity really cannot meet the load, raising it in the model hides a real problem. Report it to the design team instead.
What not to do
Do not widen the setpoints, loosen the tolerance beyond a defensible value, or oversize everything until the hours disappear. Each of these changes energy use and can be seen by a reviewer. A model with 150 explained unmet hours is stronger than a model with zero hours and unexplained equipment sizes.
The takeaway
Unmet load hours are a quality check on the whole model: loads, sizing, schedules and controls. Find the zones, find the hours, fix the cause, and write down what was done. The 300-hour limit is easy to meet in a model that is set up correctly.
Model failing on unmet hours?
We diagnose and fix unmet load hours in EnergyPlus, OpenStudio and DesignBuilder models, and document the fix for LEED and code reviewers. Let's talk.
Get in touchThis article is general guidance and reflects information available at the time of writing. Unmet load hour limits and definitions are set by the edition of ASHRAE 90.1 and the rating system that applies to your project.