A home that passes Part L can still fail its occupants in July. Part O is the check for that.

UK homes have become better insulated and more airtight, which is good for winter bills. Combined with large windows and warmer summers, it has also made overheating a real risk, especially in flats. Since June 2022, Part O of the Building Regulations has required new residential buildings in England to show that overheating has been limited. There are two ways to show it.

Route 1: the simplified method

The simplified method is a set of limits, checked without simulation. It caps the glazing area as a share of floor area, with tighter limits for the most exposed orientation, and sets minimum opening areas for removing heat. The limits depend on whether the home is in a high-risk location (parts of London and central Manchester) or elsewhere, and on whether it has cross-ventilation.

It is quick, but it is strict. Homes with generous glazing, single-aspect flats and sites where windows cannot be opened freely often cannot pass it.

Route 2: dynamic thermal modelling

The alternative is an hour-by-hour simulation following CIBSE TM59. The dwelling is modelled with standard occupancy, equipment and lighting profiles and run against a design summer year weather file, a warmer-than-typical summer chosen for the project's region. Because the profiles are fixed, results from different assessors are comparable.

The TM59 criteria

For homes that are mainly naturally ventilated, two tests apply:

The night-time bedroom test is usually the hard one. Homes that are mainly mechanically ventilated or cooled are tested against a fixed temperature limit instead.

The Part O limits on the model

Part O adds rules on top of TM59 so that the model reflects how windows can really be used:

These rules decide many projects. A flat beside a busy road may pass easily with windows open and fail once they must be closed at night. The solution then has to come from the building: external shading, lower-g-value glazing, smaller windows on the hot side, or mechanical ventilation with enough capacity. Active cooling is the last resort.

TM52 for non-domestic buildings

Offices, schools and other non-domestic buildings are assessed with CIBSE TM52. It uses the same adaptive comfort idea with three criteria: how often the threshold is exceeded, how severe the exceedance is on any one day, and an absolute upper limit. A room that fails any two of the three is classed as overheating. TM52 is often requested by planning authorities and clients, and it sits behind the first TM59 test above.

Start early

Overheating is mostly decided by orientation, glazing ratio, shading and the ability to cross-ventilate. Those are fixed at planning stage. An assessment run after planning approval can only add equipment. One run at concept stage can change the facade. It also needs to be coordinated with daylight and sunlight targets, which pull towards more glass, and with Part L, where solar gain helps in winter.

The takeaway

Part O offers a quick rule-based route and a modelled route. Most constrained sites end up on the modelled route, where the bedroom night-time test and the limits on window opening do most of the deciding. Test the design early, while shading and glazing can still be changed.

Need a TM59 or TM52 assessment?

We carry out dynamic overheating assessments to CIBSE TM59 and TM52 for planning and Building Regulations, with practical advice on shading, glazing and ventilation. Let's talk.

Get in touch

This article is general guidance and reflects information available at the time of writing. Requirements differ between England, Wales, Scotland and Northern Ireland and are updated periodically — always confirm the current Approved Document and local planning requirements.